14th Transportation Working Group Meeting
Seoul, October
19-23, 1998
Steering Commitee
HOB
TPT/14/HOD/7.5
TPT/14/HOD/7.5
SEOUL, REPUBLIC OF
KOREA
REVISED TPT-WG PROJECT
PROPOSAL GUIDELINES
Introduction
1 Members will recall
that at TPT-WG/12 in Taipei, the TPT agreed to follow an objective process for determining
whether or not proposed projects should proceed, and a set of guidelines was approved. At
TPT-WG/13 in Mexico City there was a short discussion in the Plenary meeting about the
first experience of using the guidelines. At that meeting, New Zealand as original
"designer" of the guidelines undertook to reconsider them and propose any
changes at TPT-WG/14. It is intended that the guidelines be discussed at the Heads of
Delegations meeting on Monday 19 October.
Comment
2 It should be remembered
that at TPT-WG/13 we had little practical experience with using the guidelines, and it may
help if the concepts are repeated:
- the quality of some project submissions to
the TPT had been lacking and an objective process was required to raise the standard, and
also to rank projects going to the BAC for consideration,
- the TPT should apply essentially the same
criteria as the BAC for self-funded projects, but to make a reasonable "hurdle"
for any TPT project, including those destined for BAC, there should be support from the
"sponsor" and at least two other economies before a project could be
considered,
- the 4-week rule should apply so members
can properly consider proposals in advance of a meeting. You will recall there were some
proposals that were first presented at TPT-WG/13, and some did not conform to the
guidelines.
3 One concern raised at
Mexico City was that the TPT facesheet differed from the BAC facesheet. The differences
relate to the need to consider both self-funded or APEC-funded projects, and for
co-sponsors to be identified. Once the TPT has approved a project that is intended for the
BAC, the "sponsor" only has to resubmit it to the Lead Shepherd through the
Steering Committee Coordinator in order for it to be considered by the BAC. In normal
circumstances there will be about 8 weeks to achieve this and it should be noted that the
extra work is minimal as:
- the supporting information in the
submission is the same whether for TPT or BAC consideration and only some reformatting for
BAC purposes is required,
- if APEC funding is sought, BAC itemised
budget forms have to be completed for TPT consideration anyway,
- differences between the TPT and BAC
facesheets are minimal.
- the only additional requirement is an
"undertaking" by the Lead Shepherd that the project complies with APEC
guidelines.
4 Attached is a revised
draft of the TPT guidelines, with the revisions to the text marked. The draft now
includes examples of the BAC facesheet (modified for TPT-WG purposes by including the
appropriate Steering Committee Coordinator as a signatory, assuming para 13 of the
guidelines is agreed) and BAC itemised budget forms as annexes.
Recommendation
5 It is recommended that
HODs agree to the revised guidelines.
TPT-WG : PROJECT PROPOSAL
GUIDELINES
General
1 These guidelines are
intended to improve the TPT's management of projects and the quality of information
provided to enable approval by:
- the TPT for self-funded projects,
- the TPT and the APEC Budget and
Administrative Committee (BAC) for APEC funded projects
Where APEC funding is
sought for TPT projects the TPT must work within the process established by the BAC and
described in the "Guidebook on APEC Financial Procedures". This provides that
working groups should evaluate any project proposals in April/May and submit finalised
proposals through the Lead Shepherd in June. The BAC considers WG proposals, which must be
ranked in priority order, in July/August each year.
2 The general principles
and specific procedures for the financial management of APEC funds are contained in the
BAC guidebook referred to above. While these TPT guidelines necessarily draw upon the BAC
guidelines, they are not a replacement for them and members are expected to conform to the
BAC guidelines at every stage of a project.
3 All projects intended
for either TPT or BAC consideration first require a written submission to the TPT from the
sponsoring member economy, endorsed by a minimum of two co-sponsor economies. It should
contain adequate information to enable the TPT to assess the project, and be transmitted
to members at least four weeks in advance of the TPT meeting at which it is to be
considered. Minimum contents of the submission are as follows:
A Cover sheet (Annex
A)
B Project Description,
incorporating
1 Objectives
The proposal should
have clear and specific objectives and justification which are achievable, realistic and
agreed by the project sponsors.
A description of how the
project responds to the priorities of APEC Leaders and Ministers, the Action Agenda, TPT
Action Programme and Vision Statement. If TILF Special Account Funding is sought, how the
project contributes to TILF objectives and in particular, how it addresses the goals set
out in Part I, and if applicable, Part II of the Osaka Action Agenda.
2 Linkages/duplication
The kinds of
institutions in member economies intended to benefit from the intended project. Highlight
the direct benefits to the institutions, the types of businesses in member economies which
will benefit from the project and what the direct benefits are.
How the participation of
the business/private sector and non-governmental institutions has been sought or will be
sought. Illustrate how the business/private sector are involved in the planning and
delivery of the project and whether any other APEC fora have been consulted.
How this project will add
"APEC value" (as to the potential benefits of implementing projects) in the
context of other work that might have been done elsewhere in the same field.
An indication of how the
project might contribute to related projects or activities in APEC or elsewhere.
Describe the deliverables
of the project and demonstrate how it will meet the needs of the targeted beneficiaries.
Note: Care should be
taken over proposals involving the creation of databases using APEC funds. (Generally a
database requires recurrent funding in order for information to remain relevant.) The BAC
will consider a request for a database more strongly if there has been a survey to
determine the demand for the database and the use to which it will be put, and a plan
outlining the future sustainablity of the database has been developed.
3 Methodology
A concise description
of the project's methodology.
A concise description of
the project by component, with its associated outputs clearly specified
A timetable for the
accomplishment of each component including completion of distinct project phases, i.e. the
intermediate goals. This should be reflected in a set of anticipated
"milestones" for gauging the success of the proposal
The number of APEC member
economies that will participate in this project. (Give the names of member economies
participating in each component of the project.)
4 Budget
The proposal needs to
be clear about whether it will be self funded or require APEC funding. If self-funded an
indicative budget should be provided as if APEC funding were being sought.
If APEC funding is
sought, an itemised budget for the project, including provision for any publication
and dissemination of project results, should be provided in the prescribed BAC format
(Annex B), for either the Operational Account or the TILF Special Account. The budget
should illustrate the assumptions adopted (e.g. unit costs) for the computations, and
include:
a A timetable for the
drawdown of APEC funding requested for the project, consistent with the APEC budget cycle
(i.e. January for the Operational Account and May for the TILF Special Account) including
details of any advance payment or instalment payment requested and justifications for such
requests, and
b Details of any request
for waiver or exception from the normal APEC financial rules with strong justifications
from the project sponsor.
The BAC guidelines
relating to allowable expenses shall be used in calculating project expenses such as
speakers, travel etc. While it is appreciated that the costs of services might vary
between economies, it is important for consistency within the TPT and APEC that the budget
is calculated in conformity with the BAC criteria.
5 Dissemination of
project output
A plan for the
publication and dissemination of the results of the project, including:
a. The nature of the
target audience, and, based on that audience:
b. the form and content,
c. format (e.g. hard
copies, floppy discs, Internet uploading),
d. number of copies for
the publication, and
e. assessibility of
results for the targeted audience.
f. A publicity plan for:
i. briefing the general
or specialist media about key components of the project, and
ii. the promotion of
sales or other dissemination of the final product.
g. A budget for
publication and dissemination, to form part of the itemised budget.
6 Assessment of
project
How the project
proponent will assess whether the criteria for APEC projects have been met and how the
impact of the project on expected beneficiaries will be measured.
7 Multi-year projects
It should be noted
that for projects seeking multi-year funding, approval will be given year by year; and
that approval in a single year does not imply automatic approval in subsequent years.
Selection and
prioritisation of TPT projects
4 In considering
proposals for approval/endorsement, the TPT must be mindful of broad APEC goals and values
as well as the TPT's own objectives.
5 Proposals seeking
support from the APEC Central Fund or the TILF Special Account require TPT endorsement.
Such endorsement should not be given lightly if TPT is to have credibility with the BAC.
Where funding is sought for several TPT projects, then a means of prioritising our
projects is necessary, particularly as working groups are required by the BAC to restrict
proposals funded from the Operational Account to a maximum of 15% of the OA budget in any
year.
6 The TPT therefore will
develop and follow a consistent approach to selection and prioritising of project
proposals. The information contained in project proposals should be adequate to enable the
TPT to assess the project against the selection and ranking criteria.
Methodology for ranking
projects
8 Each economy will rank
the new projects/proposals in order of priority, assigning a "1" to the most
important and lower numbers ("2";"3";"4" etc) to other
projects, using a ranking form as in the example at Annex C. The shepherds will rank the
scores each proposal receives. The combined score will determine the overall ranking of
particular projects/proposals against the list of total projects/proposals. The
project/proposal receiving the lowest score will be ranked first, with the others
in descending order. Member economies may wish to also consider the criteria in Annex D as
a basis for allocating their ranking scores.
9 In the event that two
or more projects receive equal scores, an opportunity to discuss the merits of each
proposal will be given followed by a further ranking exercise. In the event that this does
not produce a clear ranking, then the Lead Shepherd will determine the relative priority
of the "tied" proposals, in consultation with the Deputy Shepherd and Steering
Committee Coordinators.
10 The ranking process
will be used for all projects/proposals to be discussed at the 13th TPT meeting and
afterwards.
Actions following TPT and
BAC approval
Self-funded TPT Projects:
11 The TPT's
approval for a particular project shall be formally advised to the project sponsor by the
Lead Shepherd, with any conditions or requirements decided by the TPT. The project sponsor
may then commence the project and shall ensure that BAC financial guidelines are followed
as appropriate, and progress shall be reported regularly to the Lead Shepherd.
APEC-funded TPT Projects:
12 The TPT's
approval for a particular project shall be formally advised to the project sponsor by the
Lead Shepherd. The project sponsor shall then complete a proposal for APEC Operational
Account or TILF Special Account funding as appropriate and forward it to the Steering
Committee Co-ordinator for checking and onward transmission to the Lead Shepherd in
sufficient time for the Lead Shepherd to submit it to the Secretariat by the specified
deadline. The TPT submission to the BAC must be "signed off" by both the
Steering Committee Coordinator and the Lead Shepherd on the BAC facesheet (Annex E).
13 The APEC Secretariat
will advise the Lead Shepherd who will inform the Project Overseer (formerly the sponsor)
of the decision of the BAC and, if approved, the Programme Director will be able to assist
the Project Overseer with the implementation if required.
14 In cases where outside
contractors are to be employed on TPT projects, it is essential that the BAC guidelines
for selecting contractors are followed. In brief, these require that:
- for contracts of $US20,000 or below that
the TPT may select the contractor provided the Secretariat is informed of the process
followed;
- for contracts between $US20-50,000 the TPT
should prepare "requests for proposals" (RFP) in consultation with the Programme
Director, and which should be circulated to at least three prospective bidders. The TPT
may make the selection and advise the Secretariat of the process followed;
- for contracts over $US50,000 the TPT
should prepare a draft "request for proposals" (RFP) in consultation with the
Programme Director. The APEC Secretariat will circulate it to all member economies. The
TPT project overseer (or a TPT steering committee) will evaluate the bids and make
recommendations to the Secretariat
Monitoring and Review of
projects
15 The APEC Secretariat
requires all WGs to evaluate the overall performance of their projects (based on self
assessment) in line with the SOM "Guidelines for Evaluation and Reporting System for
APEC Projects". As well as enabling the TPT to fulfil its reporting requirements to
other APEC fora, regular and high quality internal evaluation of projects will assist the
TPT to put forward projects better targeted to the needs of APEC economies, and more
closely reflecting the aims of the APEC Action Agenda.
Development and
formulation of new proposals
16 All economies
proposing to sponsor an activity should submit a proposal to the Lead Shepherd of the TPT
using the guidelines in paragraphs 1A-B. The level of detail required for each of these
activities may differ, but every activity seeking TPT endorsement or APEC designation is
subject to formal discussion in the WG of a written submission based on those guidelines.
This will enable the TPT to effectively assess and evaluate all TPT projects against set
"APEC values" and TPT priorities and to subsequently monitor the project.
17 Some activities may be
externally imposed on the TPT. In this instance the Lead Shepherd, in cooperation with the
APEC Secretariat, would take appropriate action.
Proposal Development
18 These guidelines do
not preclude the submission of a "concept paper" to the TPT in order to assess
the level of interest among member economies before developing a project proposal for
formal consideration by the TPT.
Annex A
APEC TRANSPORTATION
WORKING GROUP
NEW PROJECT PROPOSAL
|
Project Title:
|
Sponsor Economy: |
Co-Sponsors:
|
Project Purpose:
|
Project Sponsor:
Name:
Title:
Organisation: |
Postal
Address:
Tel:
Fax:
Email: |
Total Project
Cost ($US): |
Self-funding:
$
Operational Account: $
TILF Special Account: $ |
Project Start
Date: |
Project Completion
Date: |
Project Milestones:
|
Signature of Sponsor: |
Date: |
Annex B
Enclosure 1
APEC OPERATIONAL ACCOUNT
ITEMIZED BUDGET FOR
FINANCIAL YEAR _______
| Items |
|
|
APEC Funding
(USD) |
Self
Financing (USD) |
| Direct
Labour |
No. of Hours |
Rate |
|
|
| -
Speaker's Honorarium |
|
|
|
|
| - Consultant
(including Researcher) Fees |
|
|
|
|
| -
Consultant's Secretary Cost |
|
|
|
|
| Travel |
|
|
|
|
| - Per Diem
(including accommodation and "additional payment") |
|
|
|
|
| - Airfare |
|
|
|
|
| - Inter-city
Transport |
|
|
|
|
| |
No. of Copies |
Unit cost |
|
|
| Publication
of report (including distribution) |
|
|
|
|
| Photocopying |
|
|
|
|
| Communications (Phone/ Fax/ Mail/ Courier) |
|
|
|
|
| Total |
|
|
|
|
Enclosure 2
APEC TILF SPECIAL
ACCOUNT :
ITEMIZED BUDGET FOR
FINANCIAL YEAR _______1
(Please tick ?/font>
.)
This project
o a. is a
seminar, symposium or short-term training course
o b. is a survey or analysis and research project
o c. is neither a nor b above but involves the provision
of equipment
| Items |
|
|
APEC Funding
(USD) |
Self
Financing (USD) |
| Direct
Labour |
No. of Hours |
Rate |
|
|
| -
Speaker's Honorarium |
|
|
|
|
| -
Translator's Fees |
|
|
|
|
| - Short-term
clerical and secretarial staff remuneration |
|
|
|
|
| - Consultant
(including Researcher) Fees |
|
|
|
|
| -
Consultant's Secretary Cost |
|
|
|
|
| Travel |
|
|
|
|
| - Per Diem
(incl. accommodation and "additional payment") |
|
|
|
|
| - Airfare |
|
|
|
|
| - Inter-city
Transport |
|
|
|
|
1 If project straddles more
than one year, please indicate only the amount of funds required for the financial year in
question.
Annex C
(EXAMPLE PROJECT RANKING
FORM)
APEC TPT-WG - PROJECT
RANKING FORM - 99th MEETING
Economy.................ANOTHER................................................
No: |
Proposed Project |
Rankings |
|
|
|
1 |
Road Transportation Harmonisation |
1 |
|
|
|
2 |
Seafarer's Training |
4 |
|
|
|
3 |
Workshop on Privatisation and Corporatisation |
2 |
|
|
|
4 |
Oil Spills Project - Mopping Up Equipment Inventory |
3 |
etc,etc
Annex D
FACTORS TO CONSIDER IN
RANKING TPT PROJECTS OR PROPOSALS
Member economies may wish
to consider the extent to which the project or proposal:
- furthers APEC's objectives of trade
and investment liberalisation
- furthers the TPT action programme, and the
goals set by Leaders/Ministers
- has the sponsorship of three or more
member economies
- adds value to existing TPT or other APEC
fora projects/proposals
- clearly identifies costs and benefits
- is self financing versus the percentage
cost that is expected to be supported by APEC funding (Central Fund or TILF Special
Account)
- could be supported financially or
otherwise by outside organisations
Annex E
FACESHEET for projects
seeking APEC funding
This is an application
for funding under the [ ] Operational Account (please tick one
[ ] TILF Special Account box only)
| Project
No. (to be filled in by Secretariat) |
|
Date
received by Secretariat |
|
| Name of
Committee/Working Group: Transportation Working Group (TPT) |
| Title of
Project:
|
| Proposing
APEC Member |
|
|
| Project
Overseer : Name, Title and Organization
|
|
| Postal
Address: |
|
|
Tel No.:
Fax No :
e-mail : |
| Financial
Information |
Total
Cost of Proposal (US$) |
Amount
being sought from APEC Central Fund (US$)
|
| Project Start Date |
Project End Date |
| Project
Purpose
|
| Signature of Project Overseer |
Date |
| Signature of TPT Steering Committee Coordinator: |
Date |
| Signature of TPT Lead Shepherd
|
Date |
This page was last updated on 12 March, 2008
|